Northwest Technologies - Portfolio Category

Asbestos and Lead

Boise Plaza Abatement
Northwest Technologies was part of a team that was involved in the total renovation of the Boise Plaza building, a six story, 240,000 SF building located in Boise, Idaho. The scope of the project for Northwest Technologies included the total demolition of ceilings, lighting, wall systems, HVAC ducting and all electrical.
Idaho State Capitol Abatement
This project included all floors of the Capitol Building, including the Dome. Project design and execution required that original historic building materials were to be reinstalled after project completion, the marble on the floors and the walls, could not be damaged. Northwest Technologies completed the work ahead of schedule and below budget while maintaining superior performance standards.

© 2009 Northwest Technologies - Boise, ID (208) 323-0757